A switchgear single line diagram looks simple: boxes, circles and lines on one page. In practice it is the document that decides whether the board you receive matches the board you thought you ordered.
Buyers who cannot read it sign the wrong drawing, and the mistake only appears at commissioning. These seven symbols are where most of the misreading happens.
Why the Single Line Diagram Matters More Than the Datasheet
The datasheet describes one cubicle. The single line diagram (SLD) describes the whole installation: how many incomers, how the busbar runs, where the metering sits, which feeders are spare, and how the earthing switch is interlocked.
It is also the drawing your supplier builds from. If the SLD is ambiguous, the factory will resolve the ambiguity its own way, and that resolution is what arrives on site.
7 Symbols Buyers Must Read Correctly
- The circuit breaker symbol. A square with a diagonal line and a small arc chute usually means a vacuum circuit breaker; an SF6 breaker is drawn the same way but the note beside it carries the type. Never assume a breaker is withdrawable just because the box is drawn large.
- The load break switch symbol. A simple open contact with a switch arm and no arc box is a load break switch. In an RMU this is normally the incoming or the ring position, and it cannot interrupt a fault.
- The fuse combination. A switch symbol in series with a rectangle is the fuse-switch combination, usually feeding a transformer. The rectangle carries the fuse rating, and that rating has to match the transformer kVA, not the cable.
- The earthing switch. A short line closing to earth through a small contact is the earthing switch. Check whether it is rated for making on a fault (class E1 or E2), because maintenance safety depends on it.
- The CT and VT blocks. Two circles on the busbar or the feeder are current transformers; a circle with a winding symbol is a voltage transformer. Their ratio and class decide whether your protection relay can be set correctly, and the details are explained in our instrument transformer guide.
- The interlock dashed line. A dashed line between two switching devices is a mechanical interlock, not a cable. If the dashed line is missing on the drawing, the interlock does not exist in the panel, and no logic in the relay will replace it. The usual arrangements are set out in our interlocking guide.
- The cable and busbar annotations. Feeder notes such as “3C×240 mm²” or “busbar 80×10” are not decoration. They set the termination size, the cable box depth and the short-time rating. A mismatch here is a site rework, not a paperwork error.
Symbol Conventions at a Glance
| Drawing symbol | What it is | What to verify on the SLD |
|---|---|---|
| Square with diagonal and arc box | Circuit breaker | Type, rating, fixed or withdrawable |
| Open contact with switch arm | Load break switch | Rated current, making and breaking capacity |
| Switch plus rectangle | Fuse-switch combination | Fuse rating against transformer kVA |
| Contact closing to earth line | Earthing switch | Making capacity class, interlock with breaker |
| Two circles on a line | Current transformer | Ratio, accuracy class, burden |
| Circle with winding | Voltage transformer | Ratio, class, fuse protection |
| Dashed line between devices | Mechanical interlock | Whether it exists in hardware, not only on paper |
| Text block at feeder | Cable or busbar size | Cross-section, length, short-time rating |
Different consultants use slightly different symbol sets, so the legend on the drawing always wins over the convention above. If the legend is missing, ask for it before approving.
Where SLDs Get Approved With the Wrong Content
- Missing spare feeders. A board drawn with two spares often arrives with one, because the spare was treated as unallocated space. Mark spares as installed cubicles, not reserved space.
- No cable box detail. The SLD shows the feeder but not the termination type. Heat-shrink, pre-moulded and screened terminations need different depths, and the depth decides the panel width.
- Interlocks described only in notes. A note saying “interlocked with earthing switch” without the dashed line often means the interlock was left to the relay logic, which is not acceptable for personnel safety.
- Metering drawn without CT ratio. The metering core and the protection core are separate; one ratio for both is a common and expensive simplification.
- Earthing switch class left open. If the class is not stated, assume the cheaper version is quoted, then confirm whether that suits your switching procedure.
Once the symbols are read correctly, the layout questions usually follow: clearances, creepage and the room around the panel are covered in our clearance and creepage guide, the part list in the MV switchgear components guide, and the protection settings in the protection relay guide. For distribution boards built around ring main units, the RMU selection guide explains which positions the drawing should contain.
FAQ
What is the difference between a single line diagram and a schematic?
The SLD shows one line per circuit and the main switching devices. A schematic shows every wire, terminal and auxiliary contact, and it is what the panel builder uses for wiring.
Who approves the SLD?
The consultant or the owner’s engineer approves it, and the supplier confirms it is buildable. Both signatures matter: one confirms the design intent, the other confirms the hardware exists.
Should spare feeders appear on the SLD?
Yes, as installed cubicles with the breaker fitted. If they are drawn as future space, they will usually be delivered as an empty gap in the board.
Can the interlock be done in software only?
No, not for personnel safety. Mechanical or key interlocks belong in hardware; relay logic may add monitoring but cannot replace the physical interlock.
How detailed should cable notes be?
Cross-section, conductor material, termination type and route length. The termination type is the one most often missing, and it is the one that decides whether the cable box fits.
Does the SLD need the CT ratio on it?
Yes, for both metering and protection cores. Without the ratio, the relay settings cannot be verified and the metering class cannot be confirmed.
About Electric-GS
Electric-GS is an OEM/ODM switchgear factory in Yueqing, Zhejiang, China. We build MV switchgear, gas-insulated ring main units, C-GIS cubicles and packaged substations from 11 kV to 33 kV, and we return a marked-up single line diagram with every quotation. Send your SLD and site conditions to info@electric-gs.com or WhatsApp +86 135 8897 8050. English site: electricgs.com. Chinese notes: electric-cn.com.